Wessex Water Sherston Install Case study




Wessex Water installed the TORiser 675x675x65mm on site at sandpits Lane, Sherston in January 2023.
WRC were in attendance to audit the installation Two units were used on three separate access covers within the road.
A class ii mortar was used to lay and level the TORiser units.
The pipe and ring were back filled to surfacing level.
A polyester resin mortar was then mixed and used to bed the manhole cover and frame.
The surfacing was then laid to level and road was re-opened to the public.
Approval for use was issued once the units had been inspected in May 2023.
Further inspection ‘s carried out and TORiser still performing as expected.
WRC were in attendance to audit the installation Two units were used on three separate access covers within the road.
A class ii mortar was used to lay and level the TORiser units.